We operate in the Oil, Gas & Power Industry in Nigeria, having executed over 60 projects since we commenced operations. Below is a list of projects we have executed, up to on going projects:
-
- Agbami FPSO Project
- ㆍStart : 2005-08
- ㆍCompletion : 2006-10
- ㆍLocation : Warri
-
- EPC3 BRT Expansion Project
- ㆍStart : 2005-06
- ㆍCompletion : 2007-12
- ㆍLocation : Bonny Island/Rivers state
-
- NLNG Plus Project - Train #6
- ㆍStart : 2005-04
- ㆍCompletion : 2008-07
- ㆍLocation : Bonny Island/Rivers state
-
- EPC for 24” Gas Pipeline For Swamp Gas Gathering Project
- ㆍStart : 2004-10
- ㆍCompletion : 2008-09
- ㆍLocation : Ogbainbiri to OB/OB
-
- QIT Crude & Condensate Heaters Interconnection Project
- ㆍStart : 2003-04
- ㆍCompletion : 2004-10
- ㆍLocation : Eket
-
- Nigeria LNG Plus Project – Train #5
- ㆍStart : 2002-11
- ㆍCompletion : 2005-06
- ㆍLocation : Bonny Island
-
- Rehabilitation of Fire Damaged NNPC Crude Oil Storage Tank(TK107)
- ㆍStart : 2002-06
- ㆍCompletion : 2004-04
- ㆍLocation : Escravos
-
- EPC for Kwale Gas Injection Upgrading Project (Phase I)
- ㆍStart : 2002-03
- ㆍCompletion : 2004-11
- ㆍLocation : Kwale to Okpai
-
- NLNG Phase 3 Gas Supply Pipeline
- ㆍStart : 2001-12
- ㆍCompletion : 2004-04